Ties
Weekly Update #31
18
November, 2004
LAST TWO TIE PROJECTS NEARING COMPLETION!!
As of November 18th, 2004, we have
installed just over the 245,000 that we had originally scheduled for
installation in the 2004 season.
The last two projects were completed over the course
of the last week and although there will be a few ties installed in some small
projects that are still remaining, the major tie projects for 2004 are now 100%
completed.
Preparations are now being made for the 2005 and
beyond tie programs as well as all of the other capital programs on both
properties. Preliminary figures indicate
we should be installing somewhere in the vicinity of 125,000 ties for the 2005
year.
¨ The LA Colo crew began
installing over 10,000 ties on the double track of the
¨ Wes Risseeuw’s tie crew
completed their last project of the year, installing 7,000 ties near
¨ Jim Nemec’s crew will continue
to install a few ties in conjunction with surfacing crews on the PRC sub until
the end of the year.
¨ Steve Koser’s tie crew also
installed over 30,000 ties this year before being converted to a steel crew to
lay CWR on the IC&E curves.
¨ Taking all things into
consideration, the siding additions, the siding extensions, the