Ties
Weekly Update #29
4
November, 2004
LAST TWO TIE PROJECTS STARTED!!
As
of November 4th, 2004, we have installed nearly 235,000 of the
245,000 ties now scheduled to be installed by November 24th
2004. The last two tie projects for 2004
were started this past week with Wes Risseeuw’s crew installing ties on the PRC
sub of the DM&E and the LA Colo crew installing ties on the
¨ Steve Koser’s crew finished
their tie installation projects for the year with the completion of a 10,000
tie project near
¨ The LA Colo crew began
installing over 10,00 ties on the double track of the Kansas City sub earlier
this week and will complete that project late next week.
¨ As of November 4 all 245,000
ties have been delivered to our properties and are either installed or on the
ground in preparation for installation.
¨ Taking all things into
consideration, the siding additions, the siding extensions, the
¨ Jim Nemec’s west tie gang
will be installing the last 2000 ties of their production year over the next
couple weeks near
¨ Wes Risseeuw’s tie crew will
install nearly 7000 ties near