Ties Weekly Update #29

4 November, 2004

 

 

LAST TWO TIE PROJECTS STARTED!!

 

As of November 4th, 2004, we have installed nearly 235,000 of the 245,000 ties now scheduled to be installed by November 24th 2004.  The last two tie projects for 2004 were started this past week with Wes Risseeuw’s crew installing ties on the PRC sub of the DM&E and the LA Colo crew installing ties on the Kansas City sub of the IC&E

 

¨       Steve Koser’s crew finished their tie installation projects for the year with the completion of a 10,000 tie project near Muscatine.  They will now install curve rail for the remainder of the year.

¨       The LA Colo crew began installing over 10,00 ties on the double track of the Kansas City sub earlier this week and will complete that project late next week.

¨       As of November 4 all 245,000 ties have been delivered to our properties and are either installed or on the ground in preparation for installation.

¨       Taking all things into consideration, the siding additions, the siding extensions, the Florence connection and the additional projects, we now expect to install over 245,000 ties this production season.

¨       Jim Nemec’s west tie gang will be installing the last 2000 ties of their production year over the next couple weeks near Wasta SD

¨       Wes Risseeuw’s tie crew will install nearly 7000 ties near Midland between now and Thanksgiving