System-Wide
Weekly Update #29
4
November 2004
This
past week has been one where the engineering forces on both properties have
mainly been doing final ballast unloading and surfacing in preparation for this
production season ending.
The eleven surfacing crews on the two
properties have surfaced nearly 760 pass miles this year already and other
engineering forces have unloaded nearly 250,000 tons of ballast this year. These crews will continue to surface until
freeze up and we expect well over 800 miles of surfacing to be completed by
year’s end.
Elsewhere on the properties the LA
Colo tie crew started installing 10,000 ties on track 1 of the double track
between Moseby Jct. and
Steve Koser’s curve rail crew has been
making excellent progress replacing worn rail in curves with new premium, head
hardened continuous welded rail, which will give us longer and better
service. The curve replacement project
will last through the second week of December.
Wes Risseeuw’s DM&E tie crew began
installing about 6,000 ties on the PRC sub in the
Rick Hanson, Track Supervisor at
The
¨ Equipment problems have been
very minor and have not been delaying any of the projects.
¨ All track ties have been
received on both properties and have been unloaded at the needed sites. Ties will soon start being delivered for the
2005 programs
¨ The E-80 bridge crews
currently have three crew working on bridges on the Tracy, Huron and PRC subs
¨ LG Everist and New Ulm
Quartzite Quarry have done an excellent job supplying this years ballast