System-Wide
Weekly Update #27
21
October 2004
Another
very exciting week on both properties as several projects got completed and the
final few projects of the year got started.
On the IC&E the Koser tie crew
finished their tie installation projects for the year this week near
On the DM&E the
Ballast unloading and surfacing
continue at record paces on both properties and we have now surpassed 700
surfacing pass miles and near 240,000 tons of ballast for the year, over 90% of
this year’s goal.
Bridge crews continue to do an
excellent job and we still expect all of their projects to be completed on
time.
¨ Equipment problems have been
very minor and have not been delaying any of the projects.
¨ All track ties have bee
received on both properties and have either been unloaded at the needed sites
are in the process of being unloaded this week.
¨ The Osmose bridge crews have
finished their projects on the DM&E and left the property leaving the E-80
crews as the only bridge contractors remaining on the property. E-80 currently has two crews working on
bridges and soon will have a third to complete this year’s bridge projects.
¨ LG Everist and New Ulm
Quartzite Quarry continue to do an excellent job
supplying ballast for all of our projects even though this year’s requirements
are nearly three times the normal level.