System-Wide
Weekly Update #26
14
October 2004
This
past week has been another very busy week for our tie production crews on both
properties with the IC&E crew installing more than 5,000 ties near
Muscatine and three crews installing over 15,000 ties on the DM&E,
including the Florence siding and connection tracks. We expect the tie projects on the Huron sub on
the DM&E and the River sub on the IC&E to be completed by the next
report, leaving only the IC&E’s Kansas City sub 10,000 ties and the
DM&E’s PRC sub 7,000 ties as the only ties remaining to be installed yet
this year on the two properties. These
last two projects should be finished by the end of the 2nd week of
November, completing the 2004 tie program of 245,000 hard wood ties.
Bruce Wold’s IC&E utility crew is
installing the
The
Ballast unloading on both properties
increased over the last week with over 15,000 tons being unloaded on the
DM&E alone and about 8,000 tons on the IC&E. This will enable the surfacing crews to
continue their aggressive surfacing schedule right up until freeze up which
typically occurs by mid November.
Bridge crews continue to make good
progress and we expect all projects to be completed on time.
¨ Equipment problems have been
very minor and have not been delaying any of the projects.
¨ Even though we have added
another 10,000 ties to the production schedule, most of these ties are already
on the property. The last shipments will
be coming from our three main suppliers, Koppers, Webster Industries, and
Intermountain Orient, by the end of the month.
¨ All five bridge crews from
Osmose and E-80 continue to do an excellent job and will completed their
respective projects on schedule.
¨ LG Everist and New Ulm
Quartzite Quarry continue to do an excellent job
supplying ballast for all of our projects even though this year’s requirements
are nearly three times the normal level.