System-Wide
Weekly Update #25
7
October 2004
This past week has again been another
very productive week on both properties as crews and managers make the final
year-end preparations to complete all projects by the end of this very
aggressive production season.
The
IC&E crews have been busy doing final surfacing across the entire system as
well as installing an additional 10,000 ties in the Quad Cities terminal area
that have been added to this year’s program.
Other crews have been doing final crossing surface work in the Calmar
area in preparation for the completion of that project. The CWR crew will begin their final effort of
the year on the
Also, preparation has been
made in the
Bruce
Wold’s utility crew in the Quad Cities area installed the cross- overs north of
Nahant and put them in service two weeks ago.
They will assemble and install the crossovers at
The
DM&E crews have been concentrating on the final tie installation on both
ends of the Huron sub. Both of these
projects expect to be completed by the middle of October, allowing for final
ballasting and surfacing after that.
Over the past two weeks two sections of track on the DM&E have been
raised to the 40 MPH level. These are
the first locations that CWR was installed this year. The first location is near Cobden on the
Surfacing
across the rest of the DM&E system is progressing well and we expect to get
all scheduled projects completed by the end of the year.
The
Cobden siding is providing immediate help for the transportation
department. Engineering forces are
making excellent progress on the
Bridge
crews on the DM&E continue to make excellent progress and the
¨ Equipment problems have been
very minor and have not been delaying any of the projects.
¨ Even though we have added
another 10,000 ties to the production schedule, most of these ties are already
on the property. The last shipments will be coming from our three main
suppliers, Koppers, Webster Industries, and Intermountain Orient, by the end of
the month.
¨ All five bridge crews from Osmose and E-80 continue to do an excellent job and will completed their respective projects on schedule.
¨ LG Everist and New Ulm Quartzite Quarry continue to do an excellent job supplying ballast for all of our projects.