System-Wide
Weekly Update #23
23
September 2004
This past week has been
another very productive week on both properties as crews and managers make the
final year end preparations to complete all projects by the end of the
production season.
The
DM&E CWR projects have been completed for weeks and the IC&E has
completed the Calmar portion as well as CWR curve patch programs on the Mason
City, Marquette, Chicago and River subs, leaving only the Kansas City sub
curves to complete this year’s CWR projects
Tie
crews are installing ties on the Huron and Black Hill subs of the DM&E and
the River sub on the IC&E and have less than 15% of the ties remaining to
be installed yet this year.
Surfacing
crews on both properties are doing an excellent job and we expect to complete
the over 800 miles of surfacing that is scheduled for this production
season. We currently have 7 production
surfacing crews of our own as well as 3 contract surfacing crews to accomplish
this ambitious goal. These crews are over 75% completed toward achieving that
lofty goal
The siding projects continue to progress
well with the completion of the Cobden siding just recently. This leaves only
the Florence connection and siding as major new construction projects to be
completed yet this year.
The bridge crews are making excellent
headway on the Sioux River Bridge near Volga and other crews are rebuilding all
of the other structures on the Huron and Tracy subs.
Two
new sets of crossovers for Muscatine and Davenport have been completed by LB
Foster at Niles, Ohio and were delivered this past week. The Davenport
crossover was installed and the Muscatine crossover will be installed in early
October.
¨
Equipment
problems that have plagued some of the crews, both Company and Contractor, seem
to be behind us. This has improved the
productivity of all crews over the past few weeks.
¨ The last shipment of ties for the DM&E project is on the property, leaving only the ties for the Florence connection left to be delivered. All ties have been delivered and unloaded on the IC&E.
¨ Both of our major ballast suppliers have been challenged by this year’s aggressive schedule, but they are both catching up with their stockpiles and we still expect to meet our aggressive ballasting requirements and surfacing goals.