System-Wide
Weekly Update #20
26
August 2004
Excellent progress has
continued throughout the past week on both CWR projects on the IC&E
railroad. The LA Colo crew is nearing
the halfway point of the 15 track miles that they are scheduled to lay in the Calmar
area and the IC&E’s CWR crew is about 1/3 completed on the curve patch
project that has taken them from the east end of the Mason City sub to the
Marquette sub, and now to the Chicago sub.
This curve patch project will continue through the end of the year on
the River and Kansas City subs.
Surfacing
crews on both properties continue to make good progress across both systems
toward the goal of surfacing over 800 pass miles.
The
siding projects on the DM&E are progressing extremely well with 4 siding
projects now nearly complete. The De
Smet extension was put into service on Friday the 20th and the
Cobden siding is expected to be completed by the second week of September. That will leave only the Florence siding to
finish later in the year to complete all the siding projects for the year.
The
bridge crews are making excellent headway on the Sioux River Bridge near Volga
and another crew has completed the rebuild of the Mine Creek Bridge at MP 196.7
on the Tracy sub.
Two
new sets of cross-overs, for Muscatine and Davenport, have been completed and
will be delivered by the end of next week and will be installed in early
September.
¨
Equipment
problems that have plagued some of the crews, both Company and Contractor, seem
to be mostly behind us, which has improved the productivity of all crews over
the past week.
¨
The
last shipment of ties for the DM&E project is on the property, leaving only
the ties for the Florence connection left to be delivered. All ties have been
delivered and unloaded on the IC&E.
¨
Both
of our major ballast suppliers have been challenged by this year’s aggressive
schedule, but they are both catching up with their stockpiles so we still
expect to meet our surfacing goals.
¨
The
Elkton siding, which was put into service the 28th of July, had its
final surfacing completed two weeks ago.
The De Smet extension was put into service Friday, the 20th
of August and the remainder of the Cobden siding is expected to be completed by
mid to late September.