System-Wide
Weekly Update #8
3
June 2004
This week crews on both properties have been
assembling switches and crossings in anticipation of installation with the
respective CWR projects on both properties.
The DM&E and IC&E railroads still have 55 miles of CWR to be
laid and 16 switches in conjunction with that rail laying. Besides those 16
switches, there are at least 21 other new switches of varying sizes going in
over both properties during the course of the year. The CWR, Tie and Surfacing projects are all progressing very well
and all are on, if not ahead of schedule. The added siding work will be
completed as we get openings in our tie and surfacing programs and we expect
all of the siding projects, except Florence
to be completed in the third quarter.
This should help with the grain harvest congestion. Slow orders continue to be removed on the
Owatonna sub on the IC&E and the Huron sub on the DM&E to further help
with traffic movements. Engineering
crews on both properties have been working long, hard hours, sometimes 7 days a
week, in preparation and during the CWR installation process.
¨
Equipment
continues to be very reliable with only minor breakdowns reported.
¨
Some
relief has been noted for the gondola supply and we have started receiving ties
and bridge material as well as being able to ship out scrap material recovered
from the CWR projects.
¨
All
new, air operated ballast cars are in service with only a very few minor
problems being noted.
¨
Birmingham
Diamonds have been unloaded with assembly scheduled for the week of June 14th
and installation the week of July 12th.
¨
Progress
is being made on the three additional siding projects that were recently
approved. These projects are: 1) an extension of 4000’ at Elkton 2) rebuilding
the Sanborn siding and 3) an extension of nearly 4000’ at De Smet.