System-Wide
Weekly Update #1
16
April 2004
This week things kicked into gear with the arrival of the RJ Corman rail crews. Up to this point, we have been limited to starting some of the bridge work and material delivery. Tie installation has started, but we have modified the original plan slightly to concentrate on getting the IC&E track south of Owatonna done sooner. Overall, the first week full week of “Capital Program 2004” went pretty well and we are solidly on schedule and on budget. The biggest concern today is the need to get more specific schedules/commitments for the remaining siding work. A few specific observations:
¨
All
major gangs have started. Concern is in
having a useful & fully trained workforce so we have been concentrating on
this training
¨
No
major equipment problems to report.
¨
Material
is readily available except bridge – so far we have it when we need it but it
is getting used as fast as delivered.
¨
Unloaded
2 rail trains on DME this week. Next
rail train expected the 2nd week of May with another following 10
days later. All rail should be here by
June 30th.
¨
10
of 53 newly leased ballast cars are on line.
We have run them thru twice – once on the Waseca sub and once on the
Owatonna sub. They work well. Concern over ballast car movement and
efficiencies remain high. As of today 10 more new ballast cars have arrived in
Chicago and will be in New Ulm for loading by Tuesday the 20th. The
remaining 33 should be coming at the rate of 6 to 10 per week.
¨
A
major shortage of gondolas is causing concern for the removal of scrap and
usable material from construction sites.
¨
Birmingham
Diamonds are completed and will be delivered the week of May 11. Expected to be installed while the Ford
plant shut down during July 4th week.
¨
Tracy
Siding is ahead of expectations. The first switch will be here May 1st
with crossover to arrive the week of May 10th. In service by May 15th. Received permits for crossing at Sale Barn
Road this week.
¨
Brandt
truck is working on unloading ties and moving ballast cars. Working from Pierre to Mankato.
¨ Tie installation is on track thus far.
¨ Rail installation just started this week and seems to be running according to plan – a little early to make a judgment.