Surfacing
Weekly Update #24
1
October 2004
SURFACING CONTINUES ON SCHEDULE
As of October 1, we have surfaced over 635 of
the 800 pass miles that we had projected to be surfaced in the 2004 production
year, well over 75% of the total miles scheduled. As of now, it appears we will meet or exceed that schedule.
¨
The
engineering management teams on both properties are currently evaluating
whether or not we need to get one more contractor to complete all of the
surfacing that we now plan to accomplish on both properties. That decision will be made by the end of the
week. This will depend a lot on our
ability to deliver ballast in front of the crews.
¨
We
added a contract surfacing crew from Progress Rail earlier this month on the
Kansas City sub and this crew will spend the remainder of the year on the
Kansas City and River subs.
¨
We
have also added a contract surfacing crew, Railworks, on the DM&E who will
work between Verdi and Huron for the remainder of the year.
¨
The
ARB surfacing crew continues to perform well on the Waseca sub of the DM&E
and will assist west of Mankato when they complete their work east of
Owatonna. We expect them to be west of
Mankato by the end of September or first of October.
¨
As
of October 1, 2004, over 200,000 tons of ballast has been distributed on both
properties. This is nearly 90% of the
230,000 tons of ballast that we now require to complete this year’s projects. There is still a significant number of
carloads of ballast that need to be moved and unloaded yet this year.
¨
We
continue to work very closely with the LG Everist Quarry and New Ulm Quartzite
Quarry to provide adequate supplies of ballast throughout this busy season.