Surfacing
Weekly Update #20
2
September 2004
SURFACING CONTINUES ON SCHEDULE
As of September 2nd, we have surfaced over
525 of the 800 pass miles that we had projected to be surfaced in the 2004
production year, over 60% of the total miles scheduled. As of now, it appears we will meet that
schedule.
¨
There
have been some minor breakdowns on the production tampers recently which have
reduced some of the pass miles we had expected to be getting from a couple of
crews, but these problems have been corrected.
We now expect to have increased production from our surfacing equipment
for the remainder of the year.
¨
We
have added a contract surfacing crew from Progress Rail last week and they will
continue to surface on the Kansas City sub in Iowa for the next four
weeks. This crew will then either
travel to the DM&E to assist with the RRIF surfacing for the remainder of
the year or finish out the year on the IC&E.
¨
We
will be adding another contracting surfacing crew, Railworks, to assist with
surfacing behind their own tie gang between De Smet and Huron on the DM&E,
plus to do additional surfacing as needed.
¨
The
ARB surfacing crew continues to perform well on the Waseca sub of the DM&E
and may assist west of Mankato when they complete their work east of Owatonna.
¨
As
of September 2, 2004, nearly 170,000 tons of ballast has been distributed on
both properties. This is nearly 70% of
the 230,000 tons of ballast that we now require to complete this year’s
projects. The amount of ballast that is
still required for the two properties is nearly ¾ of what is required in a
normal year.
¨
We
continue to work very closely with the LG Everist Quarry and New Ulm Quartzite
Quarry to provide adequate supplies of ballast throughout this busy season.