Surfacing
Weekly Update #5
13
May 2004
CONTINUING ON SCHEDULE
As of 13 May, we have surfaced over 95 of the
800 pass miles to be surfaced in 2004.
It is scheduled to be completed by November 24th. As of now, it appears we will meet and may very
well exceed that schedule. The
surfacing is slightly ahead of schedule.
¨
All
of the 53 new Ballast cars that were leased for 2 years have arrived on line
with 38 already in service and receiving very good reviews from the engineering
forces
¨
The
Brandt truck, operated by Ernie Lehmkuhl has been very instrumental in the
ballast unloading operation. This truck can pull up to 20 cars of ballast or
other material for MOW crews to unload saving on work train requirements.
¨
Surfacing
started March 17, 2004 and is progressing at nearly 20 pass miles per week.
¨
As
of 13 May 2004, over 42,500 tons (over 500 car loads) of ballast has been
delivered. This is 20% of the 200,000
tons expected to be delivered this year.
¨
The
Transportation Department continues to do an excellent job moving the loads and
empties to the needed locations.
¨
The
Owatonna sub was removed from the FRA “excepted” track status earlier this week
and we expect this area to start to be raised to FRA class 2 (25mph) as the
surfacing progresses northward