Surfacing
Weekly Update #4
6
May 2004
CONTINUING ON SCHEDULE
As of 6 May, we have surfaced over 81 of the
800 pass miles to be surfaced in 2004, scheduled to be completed by November
24th. As of now, it appears we will
meet and may very well exceed that schedule.
The surfacing is slightly ahead of
schedule.
¨
All
of the 53 new Ballast cars that were leased for 2 years have arrived on line
with over 30 already in service and receiving very good reviews from the
engineering forces
¨
Surfacing
started March 17, 2004 and is progressing at nearly 25 pass miles per week
¨
As
of 6 May 2004, over 32,500 tons (over 400 car loads) of ballast has been
delivered. This is over 15% of the
200,000 tons expected to be delivered this year.
¨
The
Transportation Department has been doing an excellent job moving the ballast
that is required on the entire property, especially on the Owatonna sub. Also,
Customer Service reps Terri Jaacks and Lisa Van Steenwyk have been invaluable
in our efforts to get the ballast loads and empties properly billed and moved
to the unloading locations and back to the pits for reloading
¨
Surfacing
crews have been working on both properties removing the winter’s slow orders
and slow orders that were placed due to geometry car readings as well as
working on capital projects.
¨
We
are doing extensive ballasting and surfacing on the Owatonna sub that is now
slow ordered to 10 mph or in the “excepted” track category and plan to have
this subdivision up to FRA class 2 by the end of June. As noted in the Tie Update section, with
expected completion of tie installation there, and removing excessive cross
level spots, we expect this track to be removed from the “excepted” status by
Friday the 14th of May.