Rail
Weekly Update #25
7
October 2004
CWR PROJECTS OVER 95%
COMPLETED!!!!
As of October 7 we have
installed just over 93 of the roughly 97 track miles to be completed by
November 19th. The L A Colo crew completed their portion of this year’s CWR
program when they finished the Calmar CWR earlier in September and the IC&E
CWR crew completed the River sub portion of the CWR program on Tuesday the 21st
of September. They will now
install an additional 10,000 ties near
On the DM&E, surfacing was
completed and the speed was raised to 40 MPH on the Cobden section of CWR
located on the
¨ Chad Roob’s crossing gang
with the assistance of Cory Lunn’s rail change out crew, have installed the
last crossing on the Tyler CWR area and will now concentrate on completing the
Florence siding and BN connection and clean up. These two young men and their
crews have now assisted with the installation of more than 20 premium mainline
switches, 20 concrete crossings and nearly 50 plank crossings.
¨ Mike Anderson, who in his
normal job is the section foreman at Tracy Minnesota, has done an excellent job
working with Mark Trudeau and coordinating all of the crews on the
¨ Randy Parmenter’s crew has
completed all of the crossings on the Calmar CWR project and will spend the
remainder of the season on clean up and other crossing projects
¨ The clean up effort on the Calmar
CWR is near completion and will be completed in front of the final surfacing
which is scheduled to be completed by the end of October.