Rail
Monthly Update # 6
11,
June 2008
SEVEN MAJOR RAIL PROJECTS SCHEDULED FOR THE
2008 PRODUCTION SEASON!! OVER 70 MILES
OF CWR TO BE INSTALLED THIS YEAR!!
With the additional $12 million in Capital we now will have seven major CWR projects to headline the 2008 production year. Six of these projects will contain new 136# CWR and the seventh will involve used 90# and 100# CWR.
¨ The first project which was
started in 2008 was one of nearly 20 miles between
¨ The second project will be
one of 7.5 miles between
¨ A third project of nearly 13
miles between
¨ The fourth project area is
one of seven miles between Judson and
¨ The fifth CWR project is one
of eight miles between
¨ The sixth and final project
for the DM&E’s portion of the 2008 CWR schedule is one of 7.5 miles west of
¨ The final major CWR project
of the year is on the IC&E and will involve about 10 miles of used CWR for
the west end of the
¨ The last of the actual CWR
projects is the annual curve project which this year will involve nearly 9
miles of premium rail for curve replacement on the KC, River,
¨ Over 50 turnouts are now
scheduled for installation in conjunction with these CWR projects as well as
other project needs. Turnouts will be
supplied by Progress Rail and Nortrak. Foremen
Trevor Nelson will lead the west utility crew on installing the turnouts and
crossings in all of the CWR areas on the Huron sub and Foreman Darren Legare will lead the east utility crew installing turnouts
and crossings in the CWR areas on the Waseca and Tracy subs. Foreman Mike Foutch will lead a similar effort
on the
¨ All CWR will be supplied by
LB Foster and Progress Rail Services.
¨ CWR will be installed by the
RJ Corman group and Railworks starting in late May with a scheduled completion
in August.