Ties
Monthly Update #6
13
June 2007
OVER 75,000 OF 185,000 TIES TO BE INSTALLED
IN 2007 ARE ALREADY INSTALLED. ELEVEN MAJOR PROJECTS PLUS SEVERAL MINOR ONES WILL
HIGHLITE THE PRODUCTION YEAR!
The
two Company tie crews and one contractor crew have already installed over
75,000 ties on the two properties on their way to a total installation number
of nearly 185,000 ties. More details of all tie projects scheduled for 2007 are
below:
¨ The first project on the two
properties to be completed was one of nearly 12,000 ties on the IC&E’s
¨ The second project on the
two properties to be completed was one of 14,000 ties on the Upper Black Hills
Subdivision and in the
¨ The third project that was
completed on the two properties was one of 20,000 ties on the Marquette
Subdivision between
¨ The next project on the two
properties scheduled to be completed will be one of 22,000 ties on the upper
end of the Marquette Subdivision, between
¨ From the Black Hills
Subdivision the West DM&E tie gang traveled to
¨ When the ties on the Lower
Black Hills Subdivision are installed, the DM&E crew will load up their
equipment and head to Huron,
¨ Once the yard ties are installed,
the DM&E tie crew will head for the IC&E where they will install 12,000
ties on the Jackson Subdivsion and 23,000 ties on the
Mason City Subdivision. 13,000 east of
Mason City, Iowa and 10,000 west of Mason City, Iowa. These projects should finish out the year for
this crew.
¨ When John Thulen’s tie crew has completed their siding work, they
will travel to
¨ From there the IC&E crew
will complete their 2007 tie installation year by installing 22,000 ties
between Chillicothe, Missouri and Polo, Missouri. The IC&E tie crew is scheduled to complete
all of their tie installation by early August and then will install curve rail
for the remainder of the 2007 production year.