Ties
Monthly Update #3
26,June 2006
SIX OF NINE MAJOR PROJECTS ALREADY
COMPLETED. TIE CREWS ALL PERFORMING UP
TO EXPECTATIONS!
Tie
crews on both properties are busy again in 2006 with over 155,000 ties
scheduled to be installed. Over 90,000
ties have already been installed in 2006 as this site gets updated. DM&E and IC&E crews are scheduled to
install 120,000 of these ties and the LA Colo tie crew will be installing the
last 35,000. For the first time, the
DM&E has combined manpower and equipment to develop a 25 man tie crew,
similar to what is used on the IC&E for better efficiency and better use of
track time. All three of these tie crews
started on April 3rd with summaries of their accomplishments to date
and future plans listed below:
¨ The DM&E tie gang, with
Foreman Wes Rissuew completed the first project of
10,000 ties west of Huron SD on the
¨ This crew is now on the PRC
sub to install over 30,000 ties between
¨ The last DM&E project is
a 17,000 tie project between
¨ The IC&E tie gang with
Foreman John Thulen, completed their first major
project of the year in early June, the installation of over 20,000 ties on the
¨ The last major tie project
now scheduled for the IC&E tie crew will be the installation of 17,000 ties
on the KC sub near
¨ The LA Colo crew has
completed two tie projects for us so far this year. They have installed 10,000 ties on the
¨ All ties are delivered and
unloaded on site for the year’s current scheduled needs.