Ties
Monthly Update #2
24,
May 2006
FOUR OF NINE MAJOR PROJECTS ALREADY
COMPLETED. TIE CREWS ALL PREFORMING UP
TO EXPECTATIONS!
Tie
crews on both properties are busy again in 2006 with over 155,000 ties
scheduled to be installed. DM&E and
IC&E crews are scheduled to install 120,000 of these ties and the LA Colo
tie crew will be installing the last 35,000. For the first time, the DM&E has combined
manpower and equipment to develop a 25 man tie crew, similar to what is used on
the IC&E for better efficiency and better use of track time. All three of these tie crews started on April
3rd with summaries of their accomplishments to date and future plans
listed below:
¨ The DM&E tie gang, with
Foreman Wes Rissuew completed the first project of
10,000 ties west of Huron SD on the
¨ Wes’ crew
started their second scheduled project of the year, nearly 14,000 ties on the
lower
¨ After the Crawford lower
Black Hills sub ties are installed, this crew will move to the Midland area of
the PRC where they will install nearly 30,000 ties from
¨ The last DM&E project is
a 17,000 tie project between
¨ The IC&E tie gang with
Foreman John Thulen, completed their first major
project of the year, the installation of over 20,000 ties on the
¨ The last major tie project
now scheduled for the IC&E tie crew will be the installation of 17,000 ties
on the KC sub near
¨ The LA Colo crew has
completed two tie projects for us so far this year. They have installed 10,000 ties on the
¨ All ties are delivered and
unloaded on site for the year’s current scheduled needs.