System-Wide
Monthly Update #10
12, October 2006
The 2006 capital program which recently received a $25 million shot in the arm, for work on the West end of the DM&E, continues to progress on schedule. Over 180,000 ties and about 70 miles of CWR have already been installed, on our way to over 240,000 ties and nearly 85 miles of CWR for the year. Total capital expenditures for the year for the engineering departments of the two railroads will top $75 million
¨ All three major CWR projects
that involved new rail were completed earlier this year. Those projects were 10 miles of rail near
¨ A 17 mile project utilizing
used rail from the UP railroad was started in mid-September and is expected to
be completed before Thanksgiving. This
rail is being laid by the LA Colo Construction Company under Project Supervisor
Jack Boxlieter.
¨ A newly added project
utilizing used rail generated by both companies, as well as some new rail, was started
on October 2nd west of
¨ The curve patch program,
which consists of over 10 miles of new and used CWR, is progressing well. The
¨ The Ossian siding has final
grading completed and the crews have been spreading out ties, OTM and rail over
the last couple weeks. The new switches will be installed during the week of
the 16th of October and final rail construction will be completed that
week. The week after ballasting and
surfacing are scheduled to begin. Surfacing will then be completed and the
siding is expected to be in service before Thanksgiving.
¨ Several of the 40 new
turnouts that are scheduled to be installed on the two properties in 2006 have
been installed thus far. Other turnouts
are scheduled to be installed soon and the last for the year are being
delivered to project areas as this web site is updated. More details on the “rail page”.
¨ All of the 150,000 ties scheduled
for installation in this year’s original capital program have been installed on
the two properties. The recent addition
of capital money has enabled us to increase our tie installation numbers by
more than 90,000 for 2006, all on the DM&E. These ties will all be installed
west of Wall,
¨ There will be several major
bridge projects on the two properties this year with the most notable being the
redecking and rail renewal on Bridge # 1500, the
¨ Surfacing estimates for 2006
are over 850 miles with over 180,000 tons of ballast used. A progress report on the surfacing schedule is
on the “surfacing page”.