System-Wide
Monthly Update #2
24, May 2006
The 2006 capital program has gotten off to a great start in April and the first half of May with two of the four CWR projects already completed and a third nearly 25% done. Over a third of the 150,000 ties projected to be installed for the year have already been installed and four of the 9 major tie projects are already finished. Highlights are listed below
¨ Of the four major CWR
projects scheduled for 2006, two of them, a ten mile project near
¨ We have done preliminary
engineering work for the Calmar siding and will be getting bids for grading
work shortly. We expect to have grading
started by the end of June and the siding in service before the end of the
year.
¨ Three of the 40 new turnouts
that are scheduled to be installed on the two properties in 2006 have been
installed thus far. Other turnouts are
scheduled to be installed soon and many are being delivered to project areas. More details on the “rail page”.
¨ There have been over 60,000
ties of the 150,000 scheduled for installation in this year’s program already
installed on the two properties. More
details of the tie projects will be on the “tie update” page.
¨ There will be several major
bridge projects on the two properties this year with the most notable being the
redecking and rail renewal on Bridge # 1500, the
¨ Surfacing estimates for 2006
are over 850 miles with over 180,000 tons of ballast used. A progress report on the surfacing schedule is
on the “surfacing page”.