Rail
Monthly Update #2
24
May 2006
TWO OF FOUR MAJOR CWR PROJECTS ALREADY
COMPLETED!! THIRD UNDERWAY!
Four major projects headline the 2006 Rail program that
will involve laying more than 60 miles of CWR and over 30 new turnouts. The first two projects, one of 10 miles on the
DM&E near Sanborn and one of 14 miles on the IC&E south of
¨ Manager of Projects
¨ Mr. Meyer also supervised
the installation of 14 miles of CWR south of
¨ Our other Manager of
Projects, Jack Boxleiter, is supervising the
installation of 11 miles of CWR in the
¨ Jack will also be assisting
with the unloading of the CWR for our curve program for 2006 over the next few
weeks. There are 80 “strings” of rail ( over 10 track miles) in this year’s curve patch program. This rail will be installed on curves and
other areas between Polo
¨ Jack and Tim are now
scheduled to share supervisory responsibilities on the last CWR project. This project will encompass over 17 track
miles between Moseby Jct
and Lawson Jct on the
¨ We have received and
unloaded 4 of the 6 CWR trains which are scheduled to be delivered in 2006. The fifth train is being unloaded in curve
locations as this website is updated.
The last train is scheduled to be delivered on May 25th and
will be unloaded that week.
¨ The # 1 major turnout project for the year will be on the double track north of
¨ Two turnouts have been
installed on the DM&E’s Sanborn CWR project area
and a third turnout has been installed for an ethanol facility in Huron. Other turnouts will be assembled and installed
on the other CWR areas soon
¨ We are also scheduled to
replace the diamond at Davis Jct.