Bridges
Monthly Update #2
24,
May 2006
MAJOR YEAR FOR BRIDGWORK!!
The two properties
will be spending nearly $5million in Capital on bridge rebuilds and repairs in
2006. This is over twice the historical
average that was spent in the bridge departments in the past. There will be 6 Company crews and as many as
four contracting crews working at one time on the two properties. There will be 4 major projects, two on each
property, and several other lesser projects over the course of the year that
will be summarized in the spot below:
·
Bridge 1500, the
·
Bridge #K716 on the north end of the
·
Another major project on the IC&E that
was completed by the E-80 contracting crew in late March was that of bridge #
S-542 at MP 8.5 on the
·
The final major bridge project is the
approach spans for bridge #1659 near Nowlin South
Dakota where a different E-80 crew is driving pile and placing concrete ballast
tubs to repair a 60 span bridge approach that was lost in a fire late last year.
This entire project is scheduled to be
completed before the end of the 2nd quarter of 2006.
·
There will be several other significant
projects that we will report on as the year goes on.