Bridges
Monthly Update #1
26
April 2006
MAJOR YEAR FOR BRIDGWORK!!
The two properties
will be spending nearly $5 million in Capital on bridge rebuilds and repairs in
2006. This is over twice the historical
average that was spent in the bridge departments in the past. There will be six Company crews and as many as
four contracting crews working at one time on the two properties. There will be 4 major projects, two on each
property, and several other lesser projects over the course of the year that
will be summarized in the spot below:
·
Bridge 1500, the
·
On the IC&E we were plagued late in 2005
by a bridge near La Crescent Minnesota that had serious sub structure problems
that caused settling of the bridge as well as line problems. This resulted in a 10mph slow order at the
location of Bridge #K716 while design work for the repairs was completed and
material ordered. An E-80 crew with a
big help from the IC&E locomotive crane and pile driver and operator Dave Maines repaired this structure in the first quarter of 2006.
The bridge now has had the slow order
removed and is again good for 286,000# loading at the track bulleting speed.
·
Another major project on the IC&E that
was completed by the E-80 contracting crew in late March was that of bridge #
S-542 at MP 8.5 on the Owatonna sub. This complete rebuild will enable this
structure to handle unlimited 286,000 # loading and will solve a 10 MPH slow
order problem in the area.
·
The final major bridge project is the
approach spans for bridge #1659 near Nowlin South
Dakota where a different E-80 crew is driving pile and placing concrete ballast
tubs to repair a 60 span bridge approach that was lost in a fire late last
year. This entire project is scheduled
to be completed before the end of the 2nd quarter of 2006.
·
There will be several other significant
projects that we will report on as the year goes on.