Ties
Monthly Update #7
19
October 2005
DOWN TO THE LAST TWO TIE PROJECTS!!
The
tie crews on both properties have already installed over 155,000 ties. This is over 75% of the 185,000 ties now
allocated for the 2005 production season. The remainder of these ties is still scheduled
to be installed with our three railroad crews by the end of October or early in
November.
¨ The DM&E West tie gang (foreman
Jim Nemec), has already installed ties on the
Crawford sub, the east end of the PRC, west end of the PRC and the upper Black
Hills subs this year. This crew has just recently completed projects near Wasta and between Wall and Quinn and will now finish the rest of the
year between JC siding and
¨ The DM&E east tie gang
(foreman Kim Camp) has completed all of his projects for 2005 last week with the
completion of the
¨
¨ Contractor LA Colo installed
over 45,000 ties on the
¨ All 185,000 ties have been
delivered and distributed on the two properties.
¨ As of October 19h,
over 155,000 ties have already been installed.