Monthly Update #4
13,
July 2005
CWR PROGRAM OVER 90% COMPLETED!!!
To date, we have installed over 36 of the roughly 40
track miles scheduled to be completed by the end of the production season. The 30 miles scheduled to be laid by RJ
Corman was completed before the end of May.
This Corman crew was the same crew that laid over 60 track miles on the
DM&E in 2004 and nearly 90 miles of CWR on the
¨ RJ Corman completed the
first 15 miles of CWR between
¨ This same Corman crew
completed the second 15 mile section of CWR north of
¨ The LA Colo crew has
completed the installation of the CWR in curves on the
¨ Steve Koser’s
crew has installed curve rail on 4 curves on the double track to complete his
crew’s work in that area this year. They
will continue northward installing ties and rail where needed and expect to
have the last CWR installed by the end of September on the River sub
¨ Darren LeGarre’s
switch and crossing crew has completed the installation of 6 Revere CWR
switches, 3 Philip SD switches and 2 New
¨ Randy Parmenter’s
switch and crossing crew has assembled and installed all of the switches in the
Plymouth CWR area and recently has renewed all of the crossings through this
project area. Over the next few weeks
they will be installing two new switches at Luana for
a new customer plus assisting with several state crossing projects.